It’s been a while since I’ve posted anything here, and we’ve received questions about dates and progress on the signs, so I figured I’d post a quick update. I personally have not been involved with these projects since they were moved onto the 2022 calendar, therefore a lack of posting here. As we can allContinue reading “August 2022 Update”
Author Archives: voiceofsouthmoorpark
More Pics
Here are a few more pics that were sent from this past Sunday.
December 13th Update
Most of the stumps that were over at Kanemoto were able to be charred this weekend. A BIG THANK YOU!!! to all the volunteers that helped to get this messy task done – Ed, Mike, Christine, Ruth and Maura! You all ROCK! There are a few left, and we are hoping to get another pileContinue reading “December 13th Update”
December 10th Update
Two of the three Torii Gates were placed last weekend. The contractor has been working this week on the island at Jersey and Main, having most of the dirt cuffed down. We need to wait to work on the island on S. Pratt Pkwy until there is an xcel energy supervisor assigned. We’d like toContinue reading “December 10th Update”
December 4th & 5th Update
Two of three Torii Gates were placed yesterday. A big THANK YOU! to all the volunteers that helped make this happen – Ed, Abe, Nadeen, Marta, Maura, Blake, Jeremiah, Tom – without your hands, it would have been impossible to complete this step all in one day. You may have seen them while driving around,Continue reading “December 4th & 5th Update”
December 3rd Update
Large boulders have all been removed from the islands. Tomorrow, Saturday the 4th, we will be placing the Torii Gates. We could use some extra working hands for this task. If you’d like to help out with some digging and moving the Torii Gates into position, please sign up to volunteer by CLICKING HERE. HereContinue reading “December 3rd Update”
December 2nd Update
Today all the large boulders were removed from the island at Quebec and Main. The work then continued at the Jersey and Main location. There are many more rocks at this location, and hopefully these can all be moved tomorrow. The next step in the process will be to regrade both of these islands andContinue reading “December 2nd Update”
Camera Anyone?
Work has begun and nearly all the existing rock from Quebec and Main have been relocated to the staging area. A security concern has come up, as they will temporarily be at risk in this highly accessible location. So…we are wondering if anyone in the community would be willing to let us borrow a trailContinue reading “Camera Anyone?”
December 1st Update
Permits are in hand, and Loco Construction will begin work tomorrow morning! Now is the time to sign up to volunteer!!! If you have questions regarding the tasks on the sign up sheet, please feel free to reach out Clicking Here. Or you can call/text Tara at 303-641-1932. Click Here to see the virtual VolunteerContinue reading “December 1st Update”
Torii Gates Are Built!
This grant was applied for quite a while ago, and with all the supply chain and economic issues we’ve faced since then, it was difficult to come up with a plan for these within our price range that would look nice and last without a lot of maintenance. Cedar Supply in Fort Collins offered usContinue reading “Torii Gates Are Built!”